 3/8/2011 5:14 PM
 
Hi,

What is an "Information required schedule" produced by the contrators site agent; which is required by the design team at the pre contract meeting.what does it contain and what format should it be in.
Any one got an example?

Thanks.....
New Post
 11/22/2011 8:56 PM
 
I think it's a level 1 schedule with intermediate milestones and key interfaces clearly identified. Will be glad to know others opinion.
Previous Previous
 
Next
 Disabled
ForumForumProject Control...Project Control...Project/Constru...Project/Constru...Information required scheduleInformation required schedule

spacer
 

To report abuse of any content on this site, please fill in the form. Please give a brief description of the rule being broken.

spacer