This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

Tank fabrication steps & Activities

Jan 26

Written by:
26/01/2010 20:11  RssIcon

Tank fabrication steps are mainly,

 

1.    Shop Activities

2.    Plate layout and marking

3.    Cutting, edge preperation

4.    Rolling/bending

5.    Inspection, NDT (incase of longitudinal welds)

6.    Fabrication of Nozzles/manways/ladder/stairs/platform etc;

7.    Blasting and Priming

 

Site Activities

 

1.    Bottom plate laying & Welding

2.    PWHT of clean out doors (if any)

3.    Installation of clean out doors(if any)

4.    Shell Plate erection/welding(1st course,2nd course etc;

5.    Roof plate erection/assembly/welding

6.    Nozzles and attachments fit-up and welding

7.    NDT ( Spot Radiography for butt welds and MT/PT for fillet welds)

8.    Water fill-up test or any other test as required by ITP

9.   Blasting of site welded areas and Painting