This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

How to Convert a Project’s WBS to Activity Codes in Oracle Primavera P6

May 17

Written by:
17/05/2012 15:00  RssIcon

Created by Plannertuts.com
The tutorial is originated from http://www.plannertuts.com/tutorials/how-to-convert-a-projects-wbs-to-activity-codes-in-oracle-primavera-p6-464/.



Download Tutorial Assets

Download the files to complete this tutorial on your own.

The idea of this tutorial was inspired by a question in LinkedIn forum, a planner have received a primavera schedule using WBS, as in the oil and gas industry it is very useful to have different layouts to present the schedule to different audience, and more importantly the Work breakdown structure is based on geographic area in the construction phase, and systems in the commissioning phase, the tutorial will use the APEX sample schedule to convert a WBS to activities codes, it is assumed you
have already worked with the Primavera P6 SDK.

Step 1 – Open the schedule.

The APEX schedule organizedby the default “classic WBS layout”.

undefined

Step 2 – Export WBS Dictionary to Excel

In P6, goto the WBS screen.  Customize the columns so only WBS code, and WBS name are displayed.

Highlight all WBS rows, copy and paste the two columns to the worksheet “WBS dictionary” of the  ”WBS-to-Activity-Code-P6.xls” file (see Tutorial Assets).  Make sure that your WBS structure is well organized (*).  It means every level must have the same exact number of characters.  In this regards P3 was more rigorous, as the structure of the WBS is defined first.  In P6, it is generated automatically.  It is very easy to edit the WBS Code, to have the same number of character for every level.

The excel formula in “column F” generates a unique list of the number of characters sort in ascending order, it is an array formula (that’s why there is curly braces between the formula, if not, use CTRL+SHIFT+ENTER to execute it).

In this example, WBS code with four characters -eg “APEX”, this is level 1.   WBS Code with 7 characters – eg “APEX.AM”, this is level 2.

Of course, L1, L2 are just used as an example, in a real project, levels are usually defined as  project, phase, sub-project, area, discipline, items, etc.

undefined

 

Step 3 – Export WBS Activity Assignment to Excel

Remove the Group and Sort by WBS,  in columns add WBS and Activity ID.

Copy and paste the two columns to the excel worksheet “Activity codes per Activity” in columns A and B.  Excel columns C through G will be generated automatically, by default, if no code is available, a ” -“ is assigned.

undefined

Step 4 – Create Activities Codes Dictionary and Import to P6

First define the new project activity codes in P6 that will represent the WBS.

undefined

Back in your excel file, goto the “activity code dictionary” worksheet.  Using an excel pivot table, the excel file will generate an activities codes dictionary that we have to load back in P6 on this worksheet.

undefined

Using the dictionary excel utility (Dictionary6v7.xls – instructions on using this file can be obtained fromhttp://support.oracle.com.  Search for “dictionary6v7.xls”), click on “Get Activity Codes”  (you need the SDK to be installed and configured).

undefined/p>

Copy and paste the activities dictionary from the excel file, for every level add a dummy “-“ without a code description, so P6 will not show the ugly “no code” when you organize by activity code for activities without a code assigned.

Now you can import back to P6  the activities codes dictionary (click “Set Activity Codes” on the Login tab).  Make sure you import to the right project.

undefined

Now your project is loaded with the activity codes dictionary.

undefined

Step 5 – Import activities codes assignment to P6

Make a new Excel export.  Select the newly defined activities codes (L1-L5) as columns in your layout.

Open the exported excel file.

Use a Vlookup formula to retrieve the values of L1, L2, L3, L4, L5 from the excel sheet Activity codes per Activity.  In the Excel file, there is sample vlookup sheet to show how the formula works.

Import the updated export file back to P6.  The WBS is now transfered to the L1-L5 project activity codes.

Step 6 – Enjoy.

Now, with a new layout the schedule is organized by activity codes.

undefined

Wrap Up

Primavera P6 has very strong activity codes capabilities.  Unfortunately, many planners use only the WBS as it is very easy and intuitive, but once you start tailoring the schedule, printing for a different purpose and audience, in a way that make a sense to them, activity codes should be used as Primavera only permits one WBS per project.

(*) : if your WBS has not the same number of character for every level, you can use alternative method, explained here.


Created by Plannertuts.com
The tutorial is originated from http://www.plannertuts.com/tutorials/how-to-convert-a-projects-wbs-to-activity-codes-in-oracle-primavera-p6-464/
.




Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer