This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

Quick Tip: How To Shade Non-Work Time on the Gantt Chart in Oracle Primavera

May 15

Written by:
15/05/2012 13:55  RssIcon

Created by Plannertuts.com
The tutorial is originated from http://www.plannertuts.com/tutorials/quick-tip-how-to-shade-non-work-time-on-the-gantt-chart-in-oracle-primavera-1106/.



It turns out that people like pictures.  Yes, that’s right, we love pictures….and we love the Gantt Chart.  What makes the Gantt Chart so essential is that it simplifies something that is complex.  It gives us a snapshot and a trend that our brain can digest rather than just text and numbers.


Getting the Gantt Chart to look the way you need it is a really key skill for Primavera users.

Recently someone asked me how to shade non-work time on the Activity Gantt Chart in Primavera P6.  They wanted to show clearly what days are workable and which are non-working on the Gantt Chart in P6.





It turns out it’s pretty simple to set but not terribly intuitive in Primavera, as some things are, which is why we post tutorials.

You can control how the Gantt Chart is shaded by setting the appropriate “Default Calendar“.

  1. From the “Enterprise” menu, select “Calendars“.
  2. Ensuring you have “Global” selected at the top, pick a default calendar from this screen by placing a checkmark next to it.



Although the Default Calendar serves a few purposes in P6, it’s also used to set the shading on the Gantt Chart.  Of course, what is shaded as non-work on the P6 Gantt depends on what level of zoom you have set your timescale.  Set the timescale to “Week / Day 1” or ”Week / Day 2” and you will see shading on the Gantt chart (as long as the default calendar has non-work days set). For most cases you will likely have a Global Calendar in the list that is similar or matches your project’s main calendar.

But what if your project uses a “Project Calendar”?

There’s no easy fix in this case.  You could create a copy of your Project Calendar and convert it to a Global Calendar, then make it the Default Calendar.  Otherwise, you’ll have to pick a Global Calendar to use for shading.   You can also turn shading right off by choosing a 24 x 7 calendar with no non-work days.

Now you have one more tool to paint a pretty picture of your project plan.

Created by Plannertuts.com
The tutorial is originated from http://www.plannertuts.com/tutorials/quick-tip-how-to-shade-non-work-time-on-the-gantt-chart-in-oracle-primavera-1106/
.



2 comment(s) so far...


Gravatar

Re: Quick Tip: How To Shade Non-Work Time on the Gantt Chart in Oracle Primavera

I justwant to ask for example I have 10days duration for t he activity and it passes thru friday and sat which I have set as non-working day, is there any way that the gantt chart will calculate the total days as 12 since fri and sat is non-working day.

By ian on   28/07/2013 05:12
Gravatar

Re: Quick Tip: How To Shade Non-Work Time on the Gantt Chart in Oracle Primavera

You will need to change your calender settings for that showing weekend as working. Otherwise it may not be possible

By Anil on   30/08/2013 23:49

Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer