This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

What does "Effort driven" option do?

Jun 22

Written by:
22/06/2016 08:13  RssIcon

 

 

What does “Effort driven” option do?

1

You may wonder what does “Effort driven” option in Task Detail Form do?

1

Here I have 2 tasks.

Task A doesn’t have Effort driven check. When I assign 2 resources to it, the Work unit for each resource doesn’t change (80h for each resource). No matter how many resource I assign, each resource will get 80h.

Now, Task B have Effort driven check. When I assign resource to it, the Work unit for each resource change (with 2 resource assign it will get 40h for each resource). And activity duration reduce to 5 days. The more resource you assign, the less unit each resource will get.

SUMMARY

So, when you have kind of activity which can be reduced duration by adding more resource, use “Effort driven” option.

 

 

Tags:
Categories:

Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer