This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!


Please read this help page before creating a blog

Latest blog entries

Turn off Auto Compute Actuals for 1 activity

Jun 21

Written by:
21/06/2016 22:08  RssIcon

Turn off Auto Compute Actuals for 1 activity


By default our project check this option like below image so that when you update Duration % complete, P6 will update Actual units for you.


When you don’t want this happen, you can turn it off. However it will apply to the whole project.

How about you want to turn it off for only one activity.

There is another way to turn it off by go to the Resource dictionary and turn off for that resource.

However it will apply to all resource assignment in your project.

It’s impossible. You want to turn off for only 1 activity.

And I find out there is 1 solution.

The option “Recalculate Actual Units and Cost when duration % complete changes” doesn’t affect activity which is “Fix Units” or “Fix Units/time”.

So you can change the Duration type of that activity to “Fix Units” or “Fix Units/time”.

Now when you update Duration % complete, it doesn’t automatically update actual units.


Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Security Code
Enter the code shown above in the box below
Add Comment   Cancel 
Search Blogs