This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

Create activity list report include predecessors and successors

Jun 21

Written by:
21/06/2016 21:05  RssIcon

Create activity list report include predecessors and successors

8

Sometimes you need to make an activity table report which also show predecessors and successors of each activity.

Here are the step how to do it.

Go to Report window and click “+” button to create a new report.

1

At “Select Subject Area” dialog, Select Activities.

2

At “Select Additional Subject Areas” dialog, Select Predecessors and Successors

3

Select Predecessors, Click Column

4

Select column you want to show. For example : Activity ID and Name. Then you should click Edit column to change the title.

56

7

You will do the same with the Successors.

Now you can print the report like this:

It show Predecessors and Successors for each activity.

 

Tags:
Categories:

Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer