This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

How to backup and restore Primavera P6 Oracle Express (XE) database

Jun 21

Written by:
21/06/2016 17:36  RssIcon

1

How to backup:

From the command prompt (go to ‘Start’ > ‘Run’ > type ‘cmd’ and click ‘OK’) using the format below

exp system/<password>@XE full=y file=<path>\xedump.dmp log=<path>\exp_xedump.log

Where:

  • <password> is the password you used when you installed P6 Standalone or Oracle XE manually.
  • <path> is the complete path to the folder where the log file and database backup dmp file are to be created (Example: file=C:\PrimaveraP6\backups\xedump.dmp log=C:\PrimaveraP6\backups\xedump.log)

Notes:

  • Be sure to remove any < > used in the above examples
  • Backup command example:  exp system/mypassword@XE full=y file=C:\PrimaveraP6\backups\xedump.dmp log=C:\PrimaveraP6\backups\exp_xedump.log
  • If any of the paths contain spaces they should be enclosed in single quotes. EX: log=’C:\My directory that has a space\exp_xedump.log’

How to restore:

From the command prompt (go to ‘Start’ > ‘Run’ > type ‘cmd’ and click ‘OK’) using the format below

imp userid=system/<password>@xe file=<path>\xedump.dmp commit=y buffer=8000000 fromuser=(admprm$pm,privprm$pm,pubprm$pm,bgjob$pm) touser=(admprm$pm,privprm$pm,pubprm$pm,bgjob$pm) log=<path>\imp_xedump.log

 

Where:

  • <password> is the password you used when you installed P6 Standalone or Oracle XE manually
  • <path> is the complete path to the folder where the existing database backup dmp file is located and where the log file will be created. (For example: file=C:\PrimaveraP6\backups\xedump.dmp log=C:\PrimaveraP6\backups\xedump_import.log)
    • If any of the paths contain spaces they should be enclosed in single quotes. EX: log=’C:\My directory that has a space\imp_xedump.log’

Note:

When importing using the import ‘touser’ option, the database users specified must already exist in the target database into which you’re importing the data.

To check whether these users exist or not:

  1. Open a new command prompt window (go to ‘Start’ > ‘Run’ > type ‘cmd’ and click ‘OK’)
  2. In the command prompt window, type: “sqlplus system/<password>@xe”
    where <password> is the password you used when you installed P6 Standalone or Oracle XE manually
  3. At the SQL> prompt, type: “select username from dba_users;”
  4. Check for the P6 schema users in the list of current database users

To create these users if the do not already exist, use the following steps:

  1. Download one of the following scripts:
  2. Review the before_import.sql script and make necessary modifications for your environment (such as tablespace locations)
  3. Open a new command prompt window (go to ‘Start’ > ‘Run’ > type ‘cmd’ and click ‘OK’)
  4. In the command prompt window, type: “sqlplus sys/<password>@xe as sysdba”
    where <password> is the password you used when you installed P6 Standalone or Oracle XE manually
  5. At the SQL> prompt, type: “@<path>\<filename>”
    where <path> is the complete path to the script and <filename> is the name of file.  Example, @C:\temp\before_import_8x.sql

Tags:
Categories:

Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer