This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

How to install Primavera P6 Professional 16.1 Stand-alone

Jun 20

Written by:
20/06/2016 21:15  RssIcon

3

After downloading the installation file from Oracle, unzip it.

1

Click on Setup

Select “Typical” and click OK

 

3

Click Install

4

After installation complete, click OK.

5

In Driver type drop-down list, select “P6 Pro Stand-alone (SQLite)”, then click Next

6

Select “Add a new standalone database and connection”. Click Next

7

Enter new password. For example “admin”. Click Next

8

You can change destination of database file, otherwise it will be stored in My Document folder.

Check on “Load Sample Data” if you want some sample project appear in your database. Uncheck it if you want your database is blank. To create database for working, we usually uncheck it.

Click Next

9

Click Finish

10

You have finished the installation.

Now we open the application.

In Start menu click on P6 Professional R16.1

Enter password. For example “admin”. Click OK

11

Click OK again. We will turn that notification off when we’re inside program.

12

Go to Admin -> Admin Preferences

Go to Industry tab and select your industry. For example “Engineering and Construction”. Then click on Close.

14

Congratulation. Now you can plan with Primavera P6.

Happy Planning:-)

Tags:
Categories:

Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer