This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

Automatically update progress in Primavera: The difference between Apply Actuals and Update Progress

Jun 20

Written by:
20/06/2016 21:06  RssIcon

2

In Primavera, when you need to make a quick update of project (Let’s say everything goes as it’s planned) we have 2 ways of automatically update progress:

  • Apply Actuals
  • Update Progress

1

Here I will only explain what is the difference between these 2 options.

The Apply Actuals function will update any activities with the “Auto Compute Actuals” checkbox marked…

PATTLNK_12212005_160054-cwilkinson-image

…whereas the Update Progress (Progress Spotlight) feature will update activities which fall within the spotlighted region regardless the status of “Auto Compute Actuals” checkbox.

PATTLNK_12212005_155938-cwilkinson-image

And this is the rule when Primavera automatically apply the Actual (in both option):

  • Apply an Actual Start to all Activities that have a Planned Start < Data Date. The Actual Start is set to the Planned Start.
  • Level of Efforts and WBS Summary activites get there dates from other activities.
  • Planned Finish is not changed.
  • Calculates Remaining Duration as the Early Finish-New Data Date.
  • Calculates Actual Duration as Original Duration-Remaining Duration.
  • Calculates Actual Units as Activity % Complete * At Complete Units..
  • If Planned Finish is < Data Date, then an Actual Finish will be applied. The Actual Finish is set to the Planned Finish.
  • Actuals are subtracted from Budgeted values to calculate Remaining values.

Tags:
Categories:

Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer