This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

A few things Engineering must do to enable the fast track execution of projects

Dec 5

Written by:
05/12/2013 21:48  RssIcon

- precise definition of interface between disciplines, through procedures, responsibility matrixes etc, to avoid "waiting on others",

- close coordination between disciplines, such as piping and civil: engineers and designers to be grouped by work areas rather than by disciplines,

- a good system in place for design changes. First, develop a strong resistance to design change and habit to strive to find alternatives. For changes that cannot be avoided, early implementation by means of identifiation of all impacts, prompt actions (E, P, C) and precise dedicated follow-up of implementation of all actions,

- focus and control of key vendor drawings (interface dwgs: GA, foundation and loads, piping connection, load list, PID, control narrative, C&E), avoiding engineering hold up ydue to vendor information,

- proper organisation for spooling, reducing the lag between design and shop ISOs, such organisation integrates both engineering and the construction contractor,

- definition of relevant early work packages, with construction, during construct-ability workshop,

- maintain up-to date bill of quantities, e.g., list of steel structures to be erected, with dwgs and material delivery dates, for Site to plan adequate resources,

- provide Site with adequate and updated list of items, material take-of, item count etc. to enable an accurate monitoring of the construction progress. The Construction progress shall indeed be measured against the up-dated work volumes. The later, which constitutes the "100%" will keep changing up to the end of Engineering. It is necessary that such changes are incorporated in the Construction progress measure in order to reflect the progress against the actual work volume,

- Implement a precise Engineering progress monitoring. Such as precise progress monitoring is one where steps are precisely and indisputably identified, such as with a binary status 0/1 (document not issued/document issued). Intermediate statuses, such as "document started" etc. shall not not considered. The individual document status is weighted by the number of documents to give the progress of a task consisting of the issue of multiple documents, such as P&IDs.

Tags:
Categories:
Location: Blogs Parent Separator MyBlog

Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer