This is a place for Registered Users to share their technical view and opinions in form of blogs which they think might be useful to the greater PCO community. We invite prolific writers to share their insights and witticisms, but remind all contributors to be mindful of any copyright rules. ProjectControlsOnline will not be held responsible for any breach in rights and responsible users will be held accounted for the same.

Please note that you may NOT get badges, stars etc. by posting blogs here as they are pretty meaningless as they do NOT make you wealthier, fitter or more attractive to the opposite sex! The best you will get from contributing here is the satisfaction/self-respect from knowing you have helped others.  So, please continue to make positive contribution to this community portal and extend whatever help you can to your fellow colleagues.  Thanks!

 

Please read this help page before creating a blog

spacer
Latest blog entries

How to manage risk in Primavera P6 Professional

Jan 26

Written by:
26/01/2013 00:19  RssIcon

Risks are uncertain events/conditions that have the potential to negatively (or positively) impact project objectives. Primavera P6 Release 8.2 Professional includes an integrated Risk Management feature that enables you to identify, categorize and prioritize risks, assign a responsible person for managing the risk, assign risks to one or more activities that may be impacted by the risk, and conduct qualitative analysis on each risk. Additionally, you have the ability to record a risk response.

Primavera generates a "Risk Score" based on information that is entered for each risk. The "Risk Score" can then be used to help you evaluate the significance of the risk. Included in this post are the first two steps in the process of using the Risk Management functionality in P6 Release 8.2. For the full tutorial please visit our main blog located here: http://mssprojectsanalytics.com/blog/bid/260308/How-to-manage-risk-in-Primavera-P6-Professional

Step 1. We will document a possible risk to our project involving the Design and Engineering process. We want to document that if the customer changes the design of our Office Building Addition, the project may incur additional costs as well as schedule delays. The image below illustrates the Design and Engineering WBS element (work breakdown structure). As you can see below, this portion of the project is currently scheduled to start on Jan. 11 and finish on Feb. 9, and the total budgeted cost is $3120. We can also view the activities comprising this WBS element and their corresponding dates & budgeted cost. Please note that we have added the "Risks" tab in our Activity Details.

Primavera Risk Management

Step 2. Access the "Risks" icon on the directory bar and click the add icon on the Command Bar to begin the process of documenting the potential risk. The details pertaining to the risk are added using the detail tabs. The "General" tab is used to identify the risk category, risk type, owner or person responsible for resolving the risk, and status. The Exposure Start and Exposure Finish dates correspond to the start and finish of the activities in the Design and Engineering WBS. These dates represent the earliest and latest dates this risk may occur. The Pre-Response Exposure Cost represents the possible cost this risk may impose, and the Post-Response Exposure Cost is the cost the risk may impose based on your risk response. We will discuss the calculations behind these values shortly. Notice that you can also provide the date the risk was identified as well as the resource that identified the risk.

Primavera P6

 

To continue learning the process of using the Risk Management functionality in P6 Release 8.2 access the remaining five steps here: http://mssprojectsanalytics.com/blog/bid/260308/How-to-manage-risk-in-Primavera-P6-Professional

 

Tags:
Categories:

25 comment(s) so far...


get redirected here

Terrific Website, Continue the very good job. Thank you!
# get redirected here

By TrackBack on   06/10/2015 02:06

More about the author

Fantastic Webpage, Keep up the very good work. Thank you!
# More about the author

By TrackBack on   10/10/2015 12:38

this contact form

Very good Web-site, Carry on the beneficial job. Thank you so much!
# this contact form

By TrackBack on   16/10/2015 17:36

garage door repairs

Lovely Webpage, Preserve the great job. Thanks.
# garage door repairs

By TrackBack on   18/10/2015 14:19

browse around here

Great page, Continue the beneficial work. Many thanks.
# browse around here

By TrackBack on   18/10/2015 18:48

nike air jordan china paypal

Release Date: December 5
# nike air jordan china paypal

By TrackBack on   06/12/2015 16:03

【送料無料】絵画:ウィリアム・ターナー「難破船」●サイズF12(60.6×50.0cm)●プレゼント・ギフト・風水にも人気な名画の絵画(油絵複製画)オーダーメイド制作◆無料で選べる額縁付き!◆:油彩画

I do not even know how I ended up here, but I thought this post was great. I don't know who you are but certainly you're going to a famous blogger if you aren't already ;) Cheers!
# 【送料無料】絵画:ウィリアム・ターナー「難破船」●サイズF12(60.6×50.0cm)●プレゼント・ギフト・風水にも人気な名画の絵画(油絵複製画)オーダーメイド制作◆無料で選べる額縁付き!◆:油彩画

By TrackBack on   14/03/2016 15:44

ダンノ(DANNO) トレーニングラダーHDX 全長900×巾50cm D-346

Quality articles or reviews is the secret to interest the people to pay a quick visit the web page, that's what this website is providing.
# ダンノ(DANNO) トレーニングラダーHDX 全長900×巾50cm D-346

By TrackBack on   14/03/2016 18:16

royaums sneakers women c 128

maccosmeticswholesaleoutlet mac loose foundation c 5 maccosmeticswholesaleoutlet too faced makeup c 23 maccosmeticswholesalers mac makeup 24pcs brushes c 1 maccosmeticswholesaleoutlet mac makeup 5pcs brushes maccosmeticswholesalers 40180 color eyeshadow c 18 3 maccosmeticswholesaleoutlet mac eyeliner gel c 28
# royaums sneakers women c 128

By TrackBack on   30/03/2016 15:15

maccosmeticswholesalers mac lady gaga c 7

maccosmeticswholesaleoutlet mac makeup 13pcs brushes maccosmeticswholesalers mac eyeshadow c 18 maccosmeticswholesalers mac makeup 8pcs brushes c 10 balenciaga brogues handbags c 1 maccosmeticswholesalers mac makeup brushes c 10 isabel marant sneakers c 2
# maccosmeticswholesalers mac lady gaga c 7

By TrackBack on   02/04/2016 03:37

maccosmeticswholesalers 40180 color eyeshadow c 18 3

maccosmeticswholesalers bobbi brown brush c 50 maccosmeticswholesalers wholesale dior makeup c 1 balenciaga giant 21 handbags c isabel marant sneakers c 2 balenciaga sneakers c 7 maccosmeticswholesaleoutlet mac lip balm sale c 10
# maccosmeticswholesalers 40180 color eyeshadow c 18 3

By TrackBack on   07/04/2016 02:16

isabel marant fall 2013 c 4

maccosmeticswholesaleoutlet mac makeup 19pcs brushes balenciaga brogues handbags c 1 balenciaga canvas handbags c 15 maccosmeticswholesaleoutlet mac makeup 12pcs brushes maccosmeticswholesaleoutlet 1439 color eyeshadow c 4 maccosmeticswholesalers com too faced cosmetics c 48
# isabel marant fall 2013 c 4

By TrackBack on   09/04/2016 16:13

maccosmeticswholesalers mac eyeliner gel c 29

isabel marant sneakers c 2 maccosmeticswholesalers mac eyeliner gel c 29 maccosmeticswholesalers urban decay cosmetics c 47 maccosmeticswholesaleoutlet bobbi brown brushes c 37 maccosmeticswholesaleoutlet urban decay makeup c 3 maccosmeticswholesaleoutlet mac makeup mascara c 14
# maccosmeticswholesalers mac eyeliner gel c 29

By TrackBack on   12/04/2016 08:24

maccosmeticswholesaleoutlet mac makeup 4pcs brushes

maccosmeticswholesalers mac makeup single brushes c others c 10 isabel marant fall 2013 c 4 maccosmeticswholesaleoutlet urban decay makeup c 3 maccosmeticswholesaleoutlet mac makeup 16pcs brushes maccosmeticswholesalers mac makeup bb cream c 14
# maccosmeticswholesaleoutlet mac makeup 4pcs brushes

By TrackBack on   15/04/2016 02:48

maccosmeticswholesaleoutlet 25 color eyeshadow c 4 1

maccosmeticswholesalers mac makeup other brushes c 1 maccosmeticswholesaleoutlet mac makeup 8pcs brushes maccosmeticswholesalers mac makeup bb cream c 14 maccosmeticswholesaleoutlet mac lip balm sale c 10 maccosmeticswholesalers mac makeup other brushes c 1 maccosmeticswholesaleoutlet 912 color eyeshadow c 4
# maccosmeticswholesaleoutlet 25 color eyeshadow c 4 1

By TrackBack on   18/04/2016 03:46

cheap jordan sneakers

Will be officially on sale in January next year, as the Air Jordan 5 Low shoes low to help the vanguard, this section Alternate '90 Bulls to our familiar black and red color rendering, silver 3M reflective tongue and black nubuck leather uppers are texture perfect emerge, tongue Jumpman Logo and inflammation in the bottom of the spray are injected with eye-catching red.
# cheap jordan sneakers

By TrackBack on   23/04/2016 05:07

http://www.naksh.co.in/images/Shoes/ADIDASShoes48.html

YouTube videos are famous in whole globe, because it is the leading video sharing site, and I become too happy by watching YouTube videos.
# http://www.naksh.co.in/images/Shoes/ADIDASShoes48.html

By TrackBack on   25/04/2016 04:34

ray ban wayfarer prezzo piu basso 2015

Hi there to all, how is all, I think every one is getting more from this website, and your views are fastidious in support of new people.
# ray ban wayfarer prezzo piu basso 2015

By TrackBack on   02/05/2016 16:49

oakley frogskins lx matte black

Wow, awesome blog format! How lengthy have you ever been blogging for? you made blogging look easy. The full glance of your web site is excellent, let alone the content
# oakley frogskins lx matte black

By TrackBack on   03/05/2016 01:03

oakley flak jacket prezzo

hi!,I like your writing very a lot! share we keep in touch more approximately your article on AOL? I require a specialist on this space to solve my problem. May be that is you! Taking a look ahead to peer you.
# oakley flak jacket prezzo

By TrackBack on   03/05/2016 05:07

occhiali da vista bambini ray ban

Hmm is anyone else having problems with the images on this blog loading? I'm trying to figure out if its a problem on my end or if it's the blog. Any responses would be greatly appreciated.
# occhiali da vista bambini ray ban

By TrackBack on   03/05/2016 09:10

2014 Nike Free 5.0 V4 da donna Scarpe da corsa - Bianco Verde

My relatives every time say that I am killing my time here at net, but I know I am getting familiarity daily by reading thes pleasant content.
# 2014 Nike Free 5.0 V4 da donna Scarpe da corsa - Bianco Verde

By TrackBack on   03/05/2016 13:20

ray ban 3030 outdoorsman

That is really interesting, You are an overly professional blogger. I have joined your feed and sit up for in quest of more of your excellent post. Also, I have shared your site in my social networks
# ray ban 3030 outdoorsman

By TrackBack on   03/05/2016 17:34

goedkoop nike air max 90

Informative article, totally what I was looking for.
# goedkoop nike air max 90

By TrackBack on   04/05/2016 02:06

collant adidas femme

Hi are using Wordpress for your site platform? I'm new to the blog world but I'm trying to get started and create my own. Do you need any html coding knowledge to make your own blog? Any help would be greatly appreciated!
# collant adidas femme

By TrackBack on   15/01/2017 00:42

Your name:
Gravatar Preview
Your email:
(Optional) Email used only to show Gravatar.
Your website:
Title:
Comment:
Security Code
CAPTCHA image
Enter the code shown above in the box below
Add Comment   Cancel 
spacer
Search Blogs
spacer